Frustration builds over five-year delay to 'vital' relief road (From Bridgwater Mercury)
Get involved! Send your photos, video, news & views by texting MERCURY NEWS to 80360 or email us
Frustration builds over five-year delay to 'vital' Colley Lane relief road
9:30am Tuesday 19th June 2012 in News
The Colley Lane Southern Access Road could improve situations like this, in Taunton Road yesterday.
FRUSTRATED motorists and businesses in Bridgwater are losing patience over a major relief road scheme which is now five years behind schedule.
Somerset County Council revealed this week that work on the long-awaited Colley Lane Southern Access Road - meant to take the strain off Taunton Road by providing a link from the south of Bridgwater to the Colley Lane industrial estate - will not begin until next April and will not be finished until late 2014.
The project has been beset by delays over the past decade.
In 2006, The Mercury reported that work was due to begin the next year and could be finished by 2009.
By 2008, with funding finally secured, we were reporting that the road could be completed by 2011.
The county council's own website was reporting this week that the project would start in November, but yesterday (Monday), the Mercury was told it would not begin until next spring.
Allan Cook, owner of Colley Lane Truck and Bus, said: “There is a lot of congestion at the moment and it will be a huge relief when this road is built. It would benefit everyone in the town and it really needs to be done.”
Kevin Toms, from U Save Motorcycle Tyres, added: “Congestion in Bridgwater has got a lot worse and we need relief roads. Traffic in Bridgwater drives you mental.”
Bridgwater MP Ian Liddell-Grainger said: “This road is vital to the town and its economy, and these delays are frustrating beyond belief.”
A Somerset County Council spokesman said: “There was a delay in the issuing of the original planning certificate because of some procedural issues, and another by negotiations over land included in the scheme because of a change in ownership.
“These have meant a delay to construction, which is now expected to begin in April next year, subject to satisfactory completion of the remaining statutory procedures.”
Comments(4)
LookingForLiars
says...
11:57am Wed 20 Jun 12
The lie's about new road's are just a shallow promise to get the house's built.
Next time have a contract to build the road's FIRST !
the voice of common sense
says...
5:50pm Wed 20 Jun 12
mobyman
says...
6:24am Thu 21 Jun 12
19th hole says...
3:33pm Tue 19 Jun 12
Is it Somerset county council ?who can always find money for projects in Taunton
Our Bridgwater Hospital went through the same problems it was going to be built with a start date of 2009 and completed in2011 needless to say this did not happen [very much the same reasons for our new road it will be needed now
not some time in the future
We have new housing estates going up like mushrooms there will be a giant power station on our door step who makes these decisions to drag out the much needed hospital
the much needed road structure
Lets have a share of the money that is allocated to Taunton
Lastly what large companies will want to invest in Bridgwater when they see things like the above problems