A worker was seriously injured after a panel fell 29 metres. <i>(Image: Office for Nuclear Regulation)</i>
A worker was seriously injured after a panel fell 29 metres. (Image: Office for Nuclear Regulation)
This article is brought to you by our exclusive subscriber partnership with our sister title USA Today, and has been written by our American colleagues. It does not necessarily reflect the view of The Herald.

A worker suffered serious injuries at Hinkley Point C in an incident in June, with contractors now being given more time to fix safety failings by the Office for Nuclear Regulation (ONR).

The worker was hurt when a formwork panel fell around 29 metres at the Hinkley Point C construction site, leading the nuclear regulator to issue safety improvement notices to two contractors.

The Office for Nuclear Regulation (ONR) served notices in June 2026 on Bouygues Travaux Publics SAS and Laing O’Rourke Delivery Limited, which operate together as the BYLOR joint venture.

The improvement notice has now been extended to allow both companies more time to comply.

The ONR said its enquiries found that BYLOR JV, in its role as contractor, "failed to ensure that construction work was planned, managed and monitored so that, so far as reasonably practicable, it was carried out without risks to health and safety."

Both notices were issued under Regulation 15(2) of the Construction (Design and Management) Regulations 2015.

The regulator said it recognised progress towards meeting the requirements of the notices had been made, and has granted an extension to allow BYLOR more time to demonstrate full compliance.

BYLOR JV now has until September 14 to comply with the notices.

The ONR confirmed there was no risk to nuclear safety, the public or the environment arising from the incident.

A spokesperson for Laing O’Rourke said: "The safety of our people is central to every decision we make and we appreciate the ONR’s recognition of the work done to date to address the issues raised.

"We will continue to work closely with the ONR to complete the remaining actions and meet the requirements of the Improvement Notice by the revised deadline."