THE timeline for completion of the first building at the Agratas gigafactory near Bridgwater will now be delayed by one year to 2027.
Leaflets distributed to households across Bridgwater, Puriton, and Woolavington detail how the timeline is “shifting slightly”, with Agratas “aiming to complete” its first building in 2027.
Construction work is already underway on Building One, which will be devoted to battery cell manufacturing, but it will also include staff welfare facilities such as a canteen. This summer, the steel framework will start going up on site.
Read More: Fears Agratas gigafactory, Bridgwater could be scaled back
Read More: Building to start in new year on first phase of Bridgwater project
The multi-billion pound facility was expected to be up and running by 2026 to provide electric vehicle batteries for Jaguar Land Rover.
Somerset Council approved plans for Building One in late 2024, which will form the first phase of the new complex.
But concerns have previously been raised by workers on-site about the sluggish rate of progress and fears the multi-billion-pound project could be scaled back.
Redesign proposals by Agratas include “making our operations more compact and even more efficient. The length of our first building will be shortened (by about 100 metres), meaning we can do more with less, cutting waste and boosting productivity without compromising on our ambition.”
In the leaflet, titled ‘An Update on Our Plans: Pioneering the Future of Battery Manufacturing in Somerset’, Agratas states that it is “dedicated to building a lasting, positive impact for Somerset and the wider region.”
The leaflet delivered to households also outlines that a series of community consultations will be taking place in early April for the latest plans, which include: the proposed new ring road design; the first phase of building adaptations; and how residents can have their say on the changes.
Agratas has also outlined the progress it has made so far, including the completion of piling for the first phase, the opening a new site entrance, and progressing work to connect to power and utilities.